Bulmershe Leisure Centre Works Update

Decrease Font Size Increase Font Size Text Size Print This Page

It is a hive of construction activity inside the new £14.5million Bulmershe Leisure Centre in Woodley this month (November). Bulmershe Leisure Centre Works continue at fast pace with lots of visible changes.

Tiling is continuing on the six-lane 25-metre swimming pool as well as in the changing rooms, and the pool’s moveable accessible lift is due to be installed. Work is also due to start tiling around the pool.

Bulmershe Leisure Centre Works
PIC BY STEWART TURKINGTON www.stphotos.co.uk

The first floor of the centre is being decorated and its door frames and screens fitted. Toilets and lockers are being fixed, and ceilings put up in all areas and light fittings installed. The reception desk’s template is also going in. Mains electric is now on across the centre, and gas and water are being plumbed in. Work on external landscaping is also due to start.

Bulmershe Leisure Centre Works
PIC BY STEWART TURKINGTON www.stphotos.co.uk

The new centre will also have a teaching pool with movable floor, a bigger gym plus a ‘live well’ (long-term condition) gym, a four-court sports hall, and an additional studio and café. It will benefit the whole community by providing up-to-date, accessible and flexible facilities, as well as preventative health services.

Opening Date

It is being built by our contractor Pellikaan Construction Ltd and once the centre is finished – it is due to open in late spring – it will be run by our partners Places Leisure.

Bulmershe Leisure Centre Works Continuing At Fast Pace

“Every time I visit, there is something new and exciting being installed. Watching this new centre come to life is a pleasure and I cannot wait for our local residents to see it, use it, and enjoy all that it will offer,” said Cllr Bill Soane, Wokingham Borough Mayor.